T-0802A
Multiple street projects throughout the zone which provide an immediate community impact. Since 2019, $10.2 million of corridor improvements that include pavement panel replacements, curb replacement, pavement markings and replacement of damaged sidewalks and/or installation of new sidewalks within the entire TIRZ 8-Gulfgate area. To date the project has installed over five miles of new sidewalks. The improvements enhance the overall experience for the TIRZ 8 community and help revitalize the area. This project was completed in phases.
Status: Phase III is currently under construction with slated completion of 2025.
- Phase I was completed in 2020 totaling $3.15 million with improvements to the following roadways:
- Airport Boulevard
- Bellfort Street,
- Crestmont Street
- Dixie Drive
- Monroe Road
- MLK Jr Boulevard
- Mykawa Road
- Reed Road
- Telephone Road
- Vasser Road
- Wayside Drive
- Phase II was completed in 2022 totaling $2.8 million with improvements to the following roadways:
- Selinsky Rd
- Wayside Drive
- Airport Blvd
- Crestmont Street
- East Orem Drive
- Phase III is currently under construction with slated completion of 2025 totaling $3.9 million with improvements to the following roadway:
- Airport Blvd from Telephone Road to Mykawa (this project includes a new water line)